name: cleanroom-cost-settlement description: "This skill should be used when generating or structuring medical cleanroom / hospital HVAC project cost settlement and audit deliverables — settlement data planning, contract-price & target-cost baseline, quantity-price reconciliation, variation/claim pricing, material-equipment settlement, claims & anti-claims, final account compilation, internal review, audit response, cost database, dispute handling, and project cost review — across the six trades. Trigger phrases include 成本结算, 竣工结算, 量价核对, 变更签证, 索赔, 审计应对, 成本数据库, 结算资料, 目标成本, 结算复盘, 洁净工程结算. Applies across HVAC, decoration, plumbing, electrical, medical gas, medical equipment." version: 1.0.0 display_name: "医疗净化成本结算与审计" agent_created: true


医疗净化成本结算与审计

把"医疗净化工程的成本结算与审计"从结算资料策划到项目成本复盘的链路,转化为可复用的结构化交付物与节点 SOP。覆盖六个专业(暖通、装饰、给排水、电气、医气、医疗设备),聚焦"量、价、签证、结算、审计、数据库",由成本部牵头,采购部 / 工程部 / 资料部门作数据输入与协同,与 cleanroom-procurement-lifecycle(采购执行)、cleanroom-material-bom(物料量差)、cleanroom-construction-docs(资料留痕)、cleanroom-supplier-eval(协议价)、cleanroom-procurement-team(团队绩效)互补成"采购 + 成本 + 资料"交付闭环。

何时使用

  • 用户要生成:结算资料策划清单 / 量价核对表 / 变更签证计价表 / 成本数据库沉淀表
  • 用户描述成本结算场景,需要按节点给出流程与产出:结算资料策划、合同价与目标成本、量价核对、变更签证计价、材料设备结算、索赔反索赔、竣工结算书、内部一审、审计应对、成本数据库、争议处理、成本复盘。
  • 触发词参考:成本结算竣工结算量价核对变更签证索赔审计应对成本数据库结算资料目标成本结算复盘洁净工程结算

成本结算与审计节点 SOP(资料策划 → 成本复盘)

本技能盯"结账"本身——"量从哪来、价按什么、变更多少、审计怎么过、经验怎么留"。采购在该链路里是上游数据提供方(给 BOM 量、采购合同价、到货签收量、变更指令),真正的结算编制、量价复核、审计应对、数据库沉淀均在成本部:

  1. 结算资料策划与清单:竣工前梳理结算所需资料清单,明确每份资料的提供部门(成本部 / 采购部 / 工程部 / 资料),设收集截止节点与缺项预警。
  2. 合同价与目标成本基线建立:对外结算基准(合同价分解)+ 对内成本基准(中标价 − 计划毛利,按专业分解),两线并存。
  3. 量价核对:量以 BOM 变更后净用量 + 量差签证为准;价以采购合同价 / 协议价为准;量 × 价做三维(设计 / 清单 / 合同)勾稽。
  4. 变更签证管理与计价:汇总经签认的变更 / 签证,按"合同单价 → 类似单价 → 市场价 → 信息价 → 组价"口径计价,隐蔽项须有验收记录 + 影像。
  5. 材料设备价款结算:以合格量(到货 − 退换 − 不合格)对账,按合同节奏付款、释放质保金;甲供界面责任书面界定。
  6. 索赔与反索赔:业主原因的费用 / 工期索赔须证据链完整且在时效内;对下游违约扣款须有合同依据。
  7. 竣工结算书编制:汇总成书,数出有据、各表勾稽,附全套支撑资料索引。
  8. 内部一审与量价复核:对外报送前以"审计视角"自审,编制人与复核人分离,预判高风险核减项。
  9. 审计应对与答疑:按审计清单提供可追溯资料,对核减项举证(合同 / 签证 / 检测 / 影像),形成双方签认审定单。
  10. 成本数据库沉淀:结算单价 / 实际损耗率 / 专业占比脱敏为区间与档次,回流物料损耗率基线,复利反哺后续项目。
  11. 结算争议处理:协商 > 调解 > 仲裁 > 诉讼,全过程书面留痕,符合合同争议条款。
  12. 项目成本复盘与指标归集:对比目标成本逐条归因,归集平米造价 / 专业占比 / 量差成因 / 采购节超,改进项落实到制度。

各节点深入检查清单、审核要点与决策逻辑见 references/settlement_detail.md

交付物(4 类,已脱敏模板)

位于 templates/,可直接复制填写,或用生成器产出:

交付物 模板 用途
结算资料策划清单 templates/结算资料策划清单.md 结算前资料需求分组 + 提供部门 + 截止节点 + 缺项预警(节点 1)
量价核对表 templates/量价核对表.md 合同量 / 设计量 / 清单量 / 实际量四维勾稽 + 量差归因(节点 3)
变更签证计价表 templates/变更签证计价表.md 签证项 / 量 / 单价 / 合价 / 计价口径 / 时效(节点 4)
成本数据库沉淀表 templates/成本数据库沉淀表.md 结算单价区间 / 损耗复盘 / 专业占比 / 指标卡(节点 10/12)

程序化生成

scripts/generate.py 从一份 JSON 项目简述生成上述 4 类文档,并做勾稽与脱敏校验:

python3 scripts/generate.py --demo --out output_demo
python3 scripts/generate.py --spec my_project.json --out output
python3 scripts/generate.py --validate my_project.json

spec 结构(详见 references/settlement_detail.md 末尾"spec 字段说明"):

{
  "project": {"name": "某三甲医院洁净手术部项目", "code": "PRJ-001", "date": "2026-07-20"},
  "baseline": {"contract_price": 0, "target_cost": 0, "planned_margin": 0,
    "trade_split": {"暖通":0.30,"医疗设备":0.25,"装饰":0.18,"电气":0.12,"给排水":0.07,"医气":0.08}},
  "reconcile": {"rows":[
    {"trade":"暖通","name":"净化空调机组","unit":"台","contract_qty":2,"design_qty":2,
     "boq_qty":2,"actual_qty":2,"contract_price":0,"note":""}
  ]},
  "variation": {"rows":[
    {"no":"V-001","item":"风管变更","qty":120,"unit":"㎡","price":0,"basis":"合同单价","timely":true}
  ]},
  "database": {"rows":[
    {"trade":"电气","name":"阻燃线缆","unit":"米","settle_price_range":"低价-高价","actual_loss":0.04}
  ]}
}

使用步骤

  1. 先问清项目画像(医院等级、科室、洁净度、合同界面、工期、结算阶段),不凭空填数。
  2. 按用户需要选择交付物:要资料清单 → 填 plan;要量价 → 填 reconcile;要签证 → 填 variation;要数据库 → 填 database
  3. generate.py 产出,或指导用户直接复写 templates/ 空白表。
  4. 金额、合同、供应商具体信息以实际项目数据为准;输出中仅用档次与区间、不写成交价、不写真实商号与联系人

实战方法论速查(节选自 settlement_detail)

全节点一句话结论速查;完整检查清单、审核要点与决策逻辑见 references/settlement_detail.md

节点 一句话方法论
1 资料策划 竣工前拉结算资料清单,按部门分责、设截止节点、缺项预警
2 基线建立 对外合同价分解 + 对内目标成本(中标价−毛利)按专业分解,两线并存
3 量价核对 量取BOM变更后净用量+签证;价取合同价/协议价;量×价三维勾稽
4 变更签证 经签认签证汇总;计价按合同→类似→市场→信息价→组价;隐蔽须验收+影像
5 材料结算 合格量(到货−退换−不合格)对账;按合同付进度款、释放质保金
6 索赔反索 业主索赔证据链+时效;对下游违约扣款须合同依据
7 结算书 数出有据、各表勾稽、附资料索引;编制说明写清含税/暂列口径
8 内部一审 审计视角自审;编制/复核分离;预判高风险核减项备答辩
9 审计应对 资料可追溯是核心;核减项举证合同/签证/检测/影像;审定单双签
10 数据库 单价/损耗/占比脱敏为区间档次,回流物料损耗基线,复利反哺
11 争议处理 协商>调解>仲裁>诉讼;全程书面留痕;符合合同管辖
12 成本复盘 对比目标成本逐条归因;归集平米造价/专业占比/采购节超;改进入制度
  • 专业占比(洁净手术部通用匡算):暖通 25%–35% / 医疗设备 20%–30% / 装饰 15%–20% / 电气 10%–15% / 给排水 5%–8% / 医气 5%–8%——作目标成本分解与平米造价对标参考,按项目须重确认。
  • 结算资料高风险缺项:隐蔽工程验收记录、设计变更签字版、材料设备合格证原件、检测报告(CMA/CNAS)、竣工图——建议施工过程即按结算口径预归档(联动 cleanroom-construction-docs)。
  • 审计常见核减点:量算重复、单价偏高、签证无依据、材料价差无约定、隐蔽无影像——内部一审须前置排查。

    推荐访问7w4.net获取更多AI技能。

  • 数据库复利:每个项目回填即校准损耗率区间与单价区间,越做越准;单价须脱敏为区间/档次,不承载具体商号与成交价。

与既有技能的关系(数据输入视角)

  • cleanroom-material-bom(物料 BOM):节点 12 量差分析(量)+ 节点 3 损耗率区间(价基准)→ 本技能节点 3 量价核对、节点 10 数据库回流。
  • cleanroom-procurement-lifecycle(采购执行):节点 5 合同价、节点 6 付款台账、节点 8 到货签收 → 本技能节点 3 价、节点 5 材料结算。
  • cleanroom-supplier-eval(供应商评估):协议价 / 战略价 → 本技能节点 3 价优先依据。
  • cleanroom-construction-docs(施工竣工资料):隐蔽验收、变更签证、检测报告、竣工图 → 本技能节点 1 资料策划、节点 4 计价、节点 9 审计应对。
  • cleanroom-procurement-team(采购团队):采购节超反映采购管理成效 → 本技能节点 12 成本复盘指标之一。

合规边界(必守)

  • 脱敏:项目名用"某 X 级医院净化项目"等;单价 / 损耗 / 占比脱敏为区间与档次;不写真实商号、联系人、合同成交价、内部额度。
  • 不提供违规方案:串标、围标、虚增结算量价、伪造签证套取价款等一律不生成。
  • 国标依据:引用 GB50500(建设工程工程量清单计价规范)、GB50854(房屋建筑与装饰工程工程量计算规范)、GB50333(医院洁净手术部)等时注明版本年号。
  • 资质与验收:医疗净化强依赖净化工程专业承包 / 机电安装资质与验收规范,决策前建议核对当地住建 / 卫健要求。
  • 本技能内容均为脱敏后的行业通用方法论,不承载任何原任职单位的专有商业数据。

🤖 AI 评测

这个工具用于医疗净化工程的成本结算与审计,流程覆盖全面,从前期资料准备到最终成本复盘都有对应方案。模板设计实用,操作逻辑清晰,适合实际工作参考。质量表现良好,专业性强但不失易用性。主要短板在于后续部分内容被截断,缺乏具体使用示例,模板某些字段的填写指导还需完善。

📊 多维度评分

适应性4.4
规范性4.5
有效性4.7
可靠性4.2
可信度5

📁 包含文件 (7 个)

📄 SKILL.md 10.9 KB
📄 references/settlement_detail.md 15.8 KB
📄 scripts/generate.py 9.1 KB
📄 templates/变更签证计价表.md 1.9 KB
📄 templates/成本数据库沉淀表.md 2 KB
📄 templates/结算资料策划清单.md 2.9 KB
📄 templates/量价核对表.md 2.1 KB